Eddy Street Parking Garage Equipment Installation Update

Dear team,

If you work in the Eddy Street office, as a reminder, if you have not been able to return a new parking garage application please be sure to do so no later than Friday, July 7.  The new gate equipment installation will begin tomorrow, July 6 and is expected to be completed by Monday, July 10.  Below you will find a timeline of the installation.  There may be construction disturbances as the new equipment is installed.  Thank you for your continued patience throughout this process.

 

Thursday 7/6

  • 6pm – 10pm – Prep work and pulling cable for information system, should not affect normal gate usage.

Friday 7/7

  • 6am – Gates will be up at all entrances/exits
  • 6am – 12pm – basement networking
  • 12pm – 7pm – Burns St. entrance work
  • 7pm – 10pm – Eddy St. entrance work

Saturday 7/8

  • 6am – 12pm – Napoleon St. entrance work
  • 12pm – 4pm – Nest work

Sunday 7/9

  • 6am – 3pm – Testing

Monday 7/10

  • 6am – 11am – Observation and testing

 

 

 